Entergy seeks regulatory approval to shift constructions costs for gas plants needed to power Meta's facility to its entire customer base.
WEST MONROE, La. (KNOE) - The City of Monroe hosted a Next Level Breakfast with Meta officials on Wednesday, May 14. The event was held to discuss developments and investments in Northeast Louisiana, ...
A Baton Rouge judge has dismissed a second challenge to Entergy's plan to power Meta's $10 billion AI data center in northeast Louisiana ... Entergy wants to build three gas-fired power plants ...
Two of the general contractors hired for the $10 billion north Louisiana Meta data center project ... The majority of the jobs created by the AI data center project in Richland Parish, an ...